POLYFILM Base Building  
   
 
POLYMER Tool Install  
   
 

Casa Conde del Mar

  • Blg. #1 & #2 & External Facilities

 

Multimix Microtechnology

  • Alcances Mécanicos:

    • 140m of Copper Pipe for Compressed Air

    • 120m of PVC for Vacuum System

    • 110m of Copper Pipe for Nitrogen System

  • Alcances Eléctricos:

    • 70m of Bussduct Installation

    • 800m os Square Duct Installation

    • 1.75m MVA Installation of Panelboards and Substation

    • 120m Lightning Fixture Installation

    • Complete Electrical Equip. Conn.

 

EATON CUTLER HAMMER

  • Alcances Mécanicos:

    • Rearrangement of Compressed Air System to Updated Layout

  • Alcances Eléctricos:

    • Rearrangement and Upgrade or Electrical Installation for New Equipment Layout

 

Banco Nacional de Costa Rica

  • Sprinkler system Installation - Main Vault and Central Bank Vault
  • Supression System Installarion for the HELI-PAD
  • Jicaral & Miramar Fire Supression System Upgrade
  • Alcances Mécanicos:

    • Design of Sprinkler System According to NFPA13

    • Installation of Carbon Steel Pipes for Fire Supression System at Basement #2, Treasury and Vaults

    • Design and Installation or Alternate Supresion system at Roof Top for Heli-Pad. Foam-Based System

    • Fire Supression System Upgrade at Jicaral's and Miramar's Offices
 

Dos Pinos - El Coyol

  • Alcances Mécanicos:

    • Installation of Building Mechanical Piping (Rain, Water, Fire Supression, Potable Water & Vents) For Buildings Expansion

    • Installation of Steam Extraction System for Case Washing System

  • Alcances Eléctricos:

    • Installation of Building electrical Services for Expansion:

      • Lightning

      • Outlets

      • Panelboards & Feeders

      • Equipment Outlets

 

 

 

Partners:
 

 

De la Iglesia Coreana, 100 este. Bº El Socorro, San Miguel, Santo Domingo de Heredia.
Tel. (506)2240-6687 / 2240-2668 / Fax. (506)2240-4473
Apdo. 269 1100 Tibás, San José, Costa Rica C.A.
contact@jgingenieros.com
www.jgingenieros.com